produces steam to drive a 225 MW steam turbine
...NOx emissions are expected to be less than 50 ppm and it is claimed that this will make it one of the cleanest thermal power plants in INDIA...'

AERIAL BUNCHED CONDUCTORS IN HT POWER DISTRIBUTION
- Er K ANAZOOYA & Er K S SOBHA

'...At present KSEB have a HT distribution network to the tune of 24612 ckt kms of 11 KV line, LT network of 124752 ckt kms, 22478 nos of 11 KV/LT transformers of capacities ranging from 50 to 500 KVA, approximately 6 lakhs of street lights and more than 45 lakhs of consumers...'

'Aerial Bunched Conductor (ABC) are composite cables comprising of 3 XLPE insulated aluminium alloy bearer / messenger wire, which carries the main weight...

BDDP - fuel selection & Generation Cost
- Er P G RAVINDRAN KUTTY & Er V RANJIT KUMAR

'...At present, Kerala has Hydro-Electric power stations with an installed capacity of 1491.5 MW...'

'...Brahmapuram Diesel Power Plant uses LSHS (Low Sulphur Heavy Stock - cheapest fuel available for power generation - less sulphur content which lowers wear, corrosion and pollution - high viscous) obtained as a residuum from the processing of BOMBAY HIGH CRUDE for normal operation and High Speed Diesel / Light Diesel Oil for starting and stopping operations...'

'...The waste heat Recovery Boiler associated with each 20 MW DG set (total 20 X 5 => 100 MW) can be used for
 